ZeroEdge | The data center your community will approve
The cloud that closes the loop

The data center your community will approve.

A community owned campus that turns the trash a town already pays to haul away into the power for an immersion cooled data center. Under the threshold most moratoriums draw. Zero water. Tenant included.

2.5 MW modules, added as the site allows 40 percent less energy than air cooling No cooling towers, no plume, no diesel farm
What we bring

Two engines. One circle.

Data center developers have the compute. Waste companies have the feedstock. The business is the handoff between them, and it runs both ways.

Our energy partner
Waste to power
Takes in
The municipal waste stream a community is already paying to haul away and bury, six days a week, every week.
Puts out
Electricity, generated on site at the community's own transfer station or landfill. Gasification, landfill gas, or an existing waste to energy plant, whichever the site supports. Where the plant gasifies, inert slag goes into road base.
Grid tied first, plant second
The campus energizes on grid power like any other site. When the plant comes online it carries the load behind the meter, and the utility becomes the backup and the buyer of surplus.
Our integration partner
Immersion cooling
Takes in
That electricity, delivered behind the meter to a node sized at 2.5 MW, under the threshold most state and local moratoriums draw.
Puts out
High-density compute for AI workloads: sealed, waterless, and quiet. No cooling towers, no plume, no diesel farm.
Equipment, not buildings
Modules are designed to be permitted as equipment rather than permanent structures in most jurisdictions, so permitting and construction can run in parallel.
The handoff runs both ways
Which is why neither engine is a vendor. They feed each other.
Power →
The plant’s electricity is what runs the node. The town’s trash powers the town’s data center.
← Materials
Every three to five years the node retires its servers, and the energy partner recovers the metals.
One campus. Two earning assets. Nothing leaves the loop.

Facilities are delivered through our integration partner and powered by our energy partner. Partner identities are disclosed under NDA during site qualification.

Under the line most moratoriums draw

Communities are not against data centers. They are against water, ratepayer costs, noise, and having no say. Take those four away and the answer changes.

50 MW
New York's executive order starts here. Most state bills draw the line at 10 to 20 MW, and a few go as low as 5. A 2.5 MW module sits under nearly all of them, and we size each campus to the line its own jurisdiction draws.
0 gal
Water the data center consumes. The immersion system is sealed. No cooling towers, no evaporation, no draw on the aquifer.
0 MW
New load on the residential grid. Once the plant is online it carries the campus; until then the site runs on grid power, and the utility stays the backup and buys the surplus.
54
Local restrictions passed in the last year, and 130 billion dollars of projects stalled. Every one of those jurisdictions is a place this model can still build.

Sized for approval means designed to be permitted as equipment rather than permanent structures in most jurisdictions, built in existing buildings, and quiet enough to sit next to a school. Yours, not a hyperscaler's.

Three ways to sit at this table

Same campus, same loop. What changes is which seat you take.

Own it

Cities, counties, tribal nations, hospitals, universities

You already produce the feedstock and you already pay to get rid of it. Put the station, the plant, and the data center on one property you own, and the waste problem pays for the power.

  • Tipping fees collected at your gate instead of paid at someone else's
  • Power with a negative fuel cost: the haulers pay for the fuel
  • A paying tenant signed before the first module energizes
  • The waste side run for you under a long term agreement
Qualify a site

Rent the compute

Inference platforms, regional neoclouds, healthcare, universities, sovereign and tribal workloads

The constraint in 2026 is energized megawatts, not GPUs. Reserve capacity on a campus that brings its own power, on a date that does not depend on a utility queue.

  • Reserved blocks priced before energize, take or pay after a proven SLA
  • Zero egress. Round trips stop inflating the bill
  • Dense, hot racks run cool in immersion
  • Single tenant campuses for data that cannot leave the fence
Reserve compute

Bring the building

Owners of powered buildings, stranded sites, and land near a transfer station

Hyperscalers reject buildings that do not fit a teardown model. We do not care if it is in a basement. If it has power, fiber, and room for a few modules, it may be a campus.

  • Existing structures, not greenfield
  • Modules designed to permit as equipment, not construction
  • Six tests, one answer, no obligation
Run the six tests

How it happens

Grid tied first, plant second. Nothing with a date on it depends on something unproven.

1

Qualify

Your site or jurisdiction goes through the six tests. You get the answer either way, and the no is as useful as the yes.

2

Sign the tenant

We bring the compute buyer to the table and size the plant to the station's intake. Both on paper before anything is built.

3

Build

One integration partner delivers the data center turnkey. Our energy partner builds the station and plant. The station earns from the first truck.

4

Operate

You own it. The waste side runs under a long term agreement, the data center is managed for you, and the loop closes.

The other cloud

The cloud was a weather word first. We are giving it back.

For thirty years "the cloud" meant machinery you were asked not to look at. Then the machinery got big enough to see from the road. A real cloud is the visible part of the water cycle: it lifts from the land and falls back on it, and nothing is consumed. That is the loop we build.

1

Waste

It begins at the community's own transfer station or landfill: the stream a town is already paying to haul away and bury.

2

Energy

Our energy partner converts that stream into electricity on site, behind the meter. The town's trash becomes the town's power.

3

Compute

That power runs a small, sealed, immersion cooled data node. No water evaporated. Sized below the thresholds moratoriums are written to stop.

4

Recovery

Metals and electronics come out at the sort line and go to reclamation, not to a container ship. Then it begins again.

Sustainability is a structure, not a percentage. "We use less of your water" is a negotiation. "We do not evaporate your water" ends the conversation and starts a different one.

Free site qualification

Send us an address, a building, or a county. We run it through the six tests and tell you what it can carry. No obligation, and every submission sharpens the map of where this can be built.

Qualify a site
Power at the site or nearby
Fiber, laid or reachable
Space for modules
Waste tonnage the station can attract
Local rules and thresholds
Water, or the absence of a need for it
ZeroEdge
Design · Implement · Orchestrate
© 2026 ZeroEdge Cloud Corporation. Tampa Bay, Florida. zeroedgecloud.com
Facilities are delivered through our integration partner and powered by our energy partner. Partner identities are disclosed under NDA during site qualification. Performance figures reflect the integration partner's validated platform.